[Ekhi-users] Ekhi temporary shutdown

RAFFAELLO BIANCO raffaello.bianco at ehu.eus
Mon Jul 12 14:19:28 CEST 2021


Hi Inigo,

  I would need 36h. I am sorry to cause you a problem. Maybe, to avoid  
this issue, the next time it would be better to prevent jobs from  
entering 48h before a scheduled shutdown.
If you can postpone the shutdown, I really appreciate that, because  
otherwise I have to spend time to double check the results and see  
what is good and what is not. However, if it is not possbile, of  
course you can go on with your plans. I will survive the extra work :)

Best,
Raffaello








Quoting Inigo Aldazabal Mensa <inigo.aldazabalm at ehu.eus>:

> Hi Raffaello,
>
> mmm I have already scheduled the downtime with the electricity people.
> When would you think it could be done. I can try to change it, but I'd
> like to avoid it if possible.
>
> Mi plan was sutting Ekhi down tomorrow at 8:30 or so.
>
> Iñigo
>
> On Mon, 12 Jul 2021 14:01:39 +0200 RAFFAELLO BIANCO
> <raffaello.bianco at ehu.eus> wrote:
>
>> Hi Inigo,
>>
>>   I would like to ask you a favor. Could it be possible to wait the
>> running jobs to complete (of course preventing the other jobs in the
>> queue from running) and only at that point shut down the machine,
>> please? Otherwise the running jobs will be abruptly interrupted,
>> causing corruption of the results. Since a job lasts at most 48h, you
>> will still be able to shut down ekhi soon.
>>
>> Thank you for your understanding,
>> Best,
>>
>> Raffaello
>>
>>
>> Quoting Inigo Aldazabal Mensa <inigo.aldazabalm at ehu.eus>:
>>
>> > Hi all,
>> >
>> > Tomorrow at about 8-9am electricity works have to be done in the CFM
>> > datacenter hosting Ekhi cluster. This works will affect the electric
>> > board powering Ekhi cluster and will last about 5 minutes, but Ekhi
>> > nodes will have to be shut down during this period, thus affecting
>> > running jobs. Ekhi access node will no be powered down and all
>> > queued jobs will be kept and as Ekhi is back online will start
>> > running.
>> >
>> > Should you have a very important reason impeding this shutdown
>> > please tell me as soon as posible. The works have to be done in any
>> > case along the week. Sorry for the short notice.
>> >
>> > Bests,
>> >
>> > Iñigo
>> >
>> >
>> >
>> >
>> >
>> >
>> >
>> >
>> > --
>> > Iñigo Aldazabal Mensa, Ph.D.
>> > HPC Computing Centre Manager / Scientific Computing Specialist
>> > Centro de Física de Materiales (CSIC-UPV/EHU)
>> > Paseo Manuel de Lardizabal, 5
>> > 20018 San Sebastian - Guipuzcoa
>> > SPAIN
>> >
>> > phone: +34-943-01-8780
>> > e-mail: inigo.aldazabal at csic.es inigo.aldazabalm at ehu.eus
>> > pgp key id: 0xDBCC8369
>> >
>> > _______________________________________________
>> > Ekhi-users mailing list
>> > Ekhi-users at list.ehu.eus
>> > http://list.ehu.eus/mailman/listinfo/ekhi-users
>>
>>
>>
>> _______________________________________________
>> Ekhi-users mailing list
>> Ekhi-users at list.ehu.eus
>> http://list.ehu.eus/mailman/listinfo/ekhi-users





More information about the Ekhi-users mailing list